Work Target |
Complete all concrete works in the marked area within 2 days |
Further delay impacts the installation of steel structure. |
Risk Exposure : $5,000 per day |
Risk Level : High |
Technical Issue |
Assembly part doesn’t match. |
Inform supplier to replace proper machine part |
Risk Exposure : $1,000 if delivery is delayed more than three days |
Risk Level : Very High |
Unsafe Conditiont |
Excavation without proper protection |
Heavy equipment is in risk |
Risk Exposure : $5,000 |
Risk Level : High |
Installation |
Alignment of the pressure gauge installed is not vertical. |
Please refer shop drawing and reinstall properly |
Risk Exposure : $500 |
Risk Level : Low |
Idle Resource |
Crane and crane operators are idle for last two days, waiting of material to erect. |
Subcontractor is not delivered material on time . |
Risk Exposure : $2,000 |
Risk Level : High |
Idle Site / Planning Issue |
Major section of the site is idle due to delay of inspection by municipality. |
Due to lack of planning and follow-up |
Risk Exposure : $10,000 per day |
Risk Level : Very High |
Non-Conformance |
Incorrect installation. Location of fittings not as per the drawing. |
Refer construction drawing and change the location. |
Risk Exposure : 15,000 per day |
Risk Level : Moderate |
Information |
Details provided in the shop drawing is not enough |
Request engineer to provide required information. |
Risk Exposure : $1,000 |
Risk Level : Low |
Security Issue |
CCTV is not functioning |
Incident monitoring is under risk |
Risk Exposure : $3,000 |
Risk Level : Moderate |
Utility Damage |
Damage to existing live water line. |
Follow suitable excavation method considering existing utility drawing |
Risk Exposure : $2,000 |
Risk Level : High |
Purchase Issue |
4th item is missing in the purchase order |
Inform supplier to deliver within 24 hours |
Risk Exposure : $5,000 |
Risk Level : High |
CVI |
Confirmation of Verbal Instructions in an informal urgent meeting in the site office. |
Hold all works today and focus on approval issues |
Risk Exposure : $4,000 |
Risk Level : High |
Unsafe Act |
Formwork installation without proper safety measures |
Warn the employee and send him for safety training. |
Risk Exposure : $10,000 |
Risk Level : High |
Testing / Inspection |
Test the pressure pipe line connections. |
Concrete work around the connection is delayed for the last 5 days. |
Risk Exposure : $1,000 |
Risk Level : Moderate |
Approval / Payment |
Inspection approval is pending for the completed manhole work. |
Payment is delayed 45 days after completion of the work |
Risk Exposure : $250 |
Risk Level : Low |
Material Wastage |
Excess material found in the store. |
Due to lack of periodic material reconciliation checks. |
Risk Exposure : $3,000 |
Risk Level : Moderate |
Quick Links |